------- 7/2025

July 2025

Back

In June and July, the work was carried out according to a joint plan.

Monolithic works:

  • Installation of staircases is underway.
  • Concreting of lift shafts is underway.
  • Concreting and reinforcement of the monolithic frame continues.
  • Installation of ventilation units is underway.

External networks:

  • Work is underway to lay a stormwater drainage system.

Sign up for a consultation

Our managers will contact you to clarify your wishes

Записатись
Sign up for a consultation
Заповніть поля для уточнення інформації нашому менеджеру
телефон має бути в форматі 0XXXXXXXXX
Poetica
2 Mechnikova Str., Kyiv Parus BС
About
Progress
Gallery
Developer
Location
News
Contacts

Client space ENSO

+38 (044) 299-50-17client@enso.ua
© Poetica 2025. All rights reserved
digital agency
FacebookIcons / Filled / InstagramCreated with Sketch.Icons / Filled / YoutubeCreated with Sketch.Icons / Filled / TelegramCreated with Sketch.