------- 12/2024

December 2024

Back

Monolithic works:

  • The main monolithic works have been completed and the "flower" has been installed.
  • Work continues on the installation of roofing elements.
  • Works are underway to equip the ventilation shafts.
  • Concreting of lift shafts is in progress.
  • Installation of ventilation units is in progress.
  • Metal embedded elements are being installed.

The stylobate:

  • Monolithic works near residential building No. 2 are nearing completion.

Sign up for a consultation

Our managers will contact you to clarify your wishes

Записатись
Sign up for a consultation
Заповніть поля для уточнення інформації нашому менеджеру
телефон має бути в форматі 0XXXXXXXXX
Poetica
2 Mechnikova Str., Kyiv Parus BС
About
Progress
Gallery
Developer
Location
News
Contacts

Client space ENSO

+38 (044) 299-50-17client@enso.ua
© Poetica 2025. All rights reserved
digital agency
FacebookIcons / Filled / InstagramCreated with Sketch.Icons / Filled / YoutubeCreated with Sketch.Icons / Filled / TelegramCreated with Sketch.