Residential Building No. 1

Section 1

Works are ongoing for the installation of external sewage networks.

Continued construction of vertical and horizontal elements (walls, columns, and slabs) on the 15th floor.

Section 2

Works are being carried out for the installation of external sewage networks. 

Formwork is being installed for the subsequent pouring of vertical and horizontal elements (walls, columns, and slabs) on the 14th floor. 

Section 3

Continued construction of vertical and horizontal elements (walls, columns, and slabs) on the 12th and 13th floors. 

Vertical elements of the monolithic frame on the 12th floor are being installed. 

Works are being carried out for the installation of external sewage networks. 

Works are ongoing for the installation of external water supply systems. 

Backfilling works are continuing. 

In all sections, installation of ventilated channels and construction of staircases are being carried out.

Sign up for a consultation

Our managers will contact you to clarify your wishes

Записатись
Sign up for a consultation
Заповніть поля для уточнення інформації нашому менеджеру
телефон має бути в форматі 0XXXXXXXXX
Poetica
2 Mechnikova Str., Kyiv Parus BС
About
Progress
Gallery
Developer
Location
News
Contacts

Client space ENSO

+38 (044) 299-50-17client@enso.ua
© Poetica 2025. All rights reserved
digital agency
FacebookIcons / Filled / InstagramCreated with Sketch.Icons / Filled / YoutubeCreated with Sketch.Icons / Filled / TelegramCreated with Sketch.