Facade works:

  • The top layer of the hinged ventilated facade and porcelain stoneware is being installed.
  • Work continues on the cladding of cold passages.
  • The installation of window slopes and ebbs is in progress.

Works on the lower floors:

Roofing:

  • Installation of decorative facade lighting is underway.
  • Fencing is being installed.

Stained glass systems:

  • Work is underway to install stained glass systems for the stylobate.
  • Double-glazed windows and doors are being installed.

Engineering networks:

  • Low-current systems are being installed.
  • Work is underway to waterproof ventilation ducts.
  • Internal and external engineering networks are being installed.

General house works:

  • Screeds are being installed in cold passages.
  • Work is underway to waterproof the basement of the stylobate.
  • Railings are being installed along the staircases.
  • The installation of reinforced concrete communication chambers continues.

Sign up for a consultation

Our managers will contact you to clarify your wishes

Записатись
Sign up for a consultation
Заповніть поля для уточнення інформації нашому менеджеру
телефон має бути в форматі 0XXXXXXXXX
Poetica
2 Mechnikova Str., Kyiv Parus BС
About
Progress
Gallery
Developer
Location
News
Contacts

Client space ENSO

+38 (044) 299-50-17client@enso.ua
© Poetica 2025. All rights reserved
digital agency
FacebookIcons / Filled / InstagramCreated with Sketch.Icons / Filled / YoutubeCreated with Sketch.Icons / Filled / TelegramCreated with Sketch.